Utah Court of Appeals

Can construction contractors recover for orally requested extra work? Uhrhahn Construction v. Hopkins Explained

2008 UT App 41
No. 20060616-CA
February 22, 2008
Affirmed in part and Reversed in part

Summary

A construction dispute arose when homeowner Hopkins regularly requested oral changes to written construction proposals that required written change orders, and contractor Uhrhahn performed the extra work but was not fully paid. After a bench trial, the court ruled for Uhrhahn on both breach of contract and mechanic’s lien claims, awarding damages and attorney fees.

Analysis

Construction projects frequently involve changes and additions beyond the original contract scope. But what happens when a written construction contract requires all changes to be in writing, yet the parties proceed with oral modifications? The Utah Court of Appeals addressed this common scenario in Uhrhahn Construction v. Hopkins.

Background and Facts

Uhrhahn Construction entered into written proposals with the Hopkins family for partial construction of their house. Each proposal explicitly stated that “any alteration or deviation from above specifications involving extra costs will be executed only upon written orders.” Despite this provision, Hopkins regularly made oral requests for additional work, which Uhrhahn performed. Hopkins paid invoices for some of the extra work labeled as “change orders,” but a dispute arose over defective Durisol blocks that increased installation costs. When Hopkins refused to pay for the additional expenses, Uhrhahn filed a mechanic’s lien enforcement action.

Key Legal Issues

The court addressed whether parties could create an implied-in-fact contract allowing oral modifications despite written change order requirements, and whether the mechanic’s lien enforcement action was timely filed under Utah Code section 38-1-11.

Court’s Analysis and Holding

The court affirmed that Hopkins waived the written change order requirement through his conduct. The elements for an implied-in-fact contract were satisfied: Hopkins repeatedly requested extra work orally, Uhrhahn expected compensation, and Hopkins knew Uhrhahn expected payment—evidenced by his payment of previous change order invoices. However, the court reversed the mechanic’s lien ruling because Uhrhahn failed to adequately brief the timeliness issue, and the record suggested the enforcement action was filed three days late.

Practice Implications

This decision demonstrates that written change order provisions can be waived through consistent course of dealing. Property owners who regularly request oral changes and pay for extra work may be estopped from later claiming contract protection. For contractors, the decision emphasizes the critical importance of ensuring mechanic’s lien enforcement actions are filed within statutory deadlines and that trial counsel adequately brief timeliness issues on appeal.

Original Opinion

Link to Original Case

Case Details

Case Name

Uhrhahn Construction v. Hopkins

Citation

2008 UT App 41

Court

Utah Court of Appeals

Case Number

No. 20060616-CA

Date Decided

February 22, 2008

Outcome

Affirmed in part and Reversed in part

Holding

Parties to a construction contract can waive written change order requirements through conduct and create an implied-in-fact contract permitting oral modifications, but a mechanic’s lien enforcement action must be timely filed within the statutory period.

Standard of Review

Clear error for factual findings; correctness for questions of law including statutory interpretation and contract existence; abuse of discretion for damages awards

Practice Tip

When pursuing mechanic’s lien enforcement actions, ensure comprehensive factual findings establish the last date of work or material delivery to prove timely filing within the statutory deadline.

Need Appellate Counsel?

Lotus Appellate Law handles appeals before the Utah Court of Appeals, Utah Supreme Court, California Court of Appeal, and the United States Court of Appeals for the Tenth Circuit.

Related Court Opinions

    • Utah Supreme Court

    Pangea Technologies v. Internet Promotions

    May 18, 2004

    Rule 64D(i) requires that a garnishee be afforded a hearing before it can be found liable to a plaintiff and have a judgment entered against it.
    • Appellate Procedure
    • |
    • Due Process
    • |
    • Statutory Interpretation
    Read More
    • Utah Court of Appeals

    Hansen & Mecham v. Hansen

    February 3, 2022

    Summary judgment was improper where defendant’s sworn declaration created a genuine dispute of material fact regarding whether a condition precedent to a guaranty was satisfied, and where the court granted summary judgment on causes of action not requested in the motion.
    • Appellate Procedure
    • |
    • Contract Interpretation
    • |
    • Evidence and Admissibility
    • |
    • Summary Judgment
    Read More
About these Decision Summaries

Lotus Appellate Law publishes these summaries to keep practitioners informed — not as legal advice. Each case turns on its own facts. If a decision here is relevant to your matter, we’re happy to discuss it.