Utah Court of Appeals

When can construction owners withhold progress payments for contractor delays? Globe Contracting v. Hour Explained

2025 UT App 98
No. 20240058-CA
July 3, 2025
Affirmed in part and Reversed in part

Summary

Globe Contracting sued Dr. Raymond Hour for breach of a construction contract after Hour stopped making the final three progress payments. Hour counterclaimed, arguing Globe breached first by delays and defective work. The district court ruled Hour breached without justification and awarded Globe damages, prejudgment interest, costs, and attorney fees under Utah Code section 13-8-5.

Analysis

In Globe Contracting v. Hour, the Utah Court of Appeals addressed when construction project owners may justifiably withhold progress payments from contractors who experience delays. The case provides important guidance on contract interpretation and the application of Utah’s construction payment statutes.

Background and Facts

Globe Contracting agreed to construct an office building for Dr. Hour’s chiropractic clinic for $650,000, with construction to be substantially completed within 210 days of permit issuance. The contract allowed Hour to withhold payments under four specific circumstances: defective work not remedied, Globe’s failure to pay subcontractors, Globe’s failure to pay for labor/materials, or damage caused by Globe to another contractor. When construction was delayed by weather and concealed debris, Hour sent termination notices in June and July 2016 but ultimately gave Globe until September to complete the work. Hour stopped making progress payments after July 2016, and Globe continued working until September when Hour officially terminated the contract.

Key Legal Issues

The central issue was whether Hour was justified in withholding progress payments based on Globe’s alleged breaches: performing defective work, failing to pay subcontractors, failing to complete the project timely, and hiring an unlicensed subcontractor. The case also involved the application of Utah Code section 13-8-5, which the trial court used to award prejudgment interest, costs, and attorney fees.

Court’s Analysis and Holding

The Court of Appeals affirmed that Hour materially breached by withholding payments without justification. Regarding the delay claim, the court found that time was not of the essence in this construction contract, distinguishing it from real estate contracts where courts more readily imply such terms. Even if time were material, the delays were caused by weather and Hour’s own change orders, which the contract expressly allowed to extend the completion date. The court rejected Hour’s other breach claims, finding insufficient evidence that defective work existed when payments stopped or that Globe failed to pay subcontractors. Significantly, the court reversed the awards of prejudgment interest and costs under section 13-8-5, holding that this retention proceeds statute applies only when funds are actually retained in escrow accounts pursuant to contract terms, not when payments are simply withheld due to alleged breaches.

Practice Implications

This decision clarifies that construction contract payment disputes are governed by traditional breach of contract principles rather than Utah’s specialized retention proceeds statute. Practitioners should carefully draft contracts to specify when withholding payments is justified and ensure compliance with marshaling requirements when challenging factual findings on appeal. The court’s analysis of attorney fee awards for travel time by non-local counsel also provides guidance for fee applications in construction cases.

Original Opinion

Link to Original Case

Case Details

Case Name

Globe Contracting v. Hour

Citation

2025 UT App 98

Court

Utah Court of Appeals

Case Number

No. 20240058-CA

Date Decided

July 3, 2025

Outcome

Affirmed in part and Reversed in part

Holding

A construction contractor’s failure to timely complete a project does not justify the owner’s withholding of progress payments when the delays were caused by weather and owner-initiated change orders that extended the completion date under the contract terms.

Standard of Review

Correctness for contract interpretation questions; clear error for factual determinations including breach of contract findings and damages awards; correctness for statutory construction and prejudgment interest determinations; abuse of discretion for attorney fee amounts with correctness for legal errors

Practice Tip

When seeking attorney fees for travel time by non-local counsel, ensure the district court provides a clear explanation for why such fees are reasonable under the specific circumstances to facilitate appellate review.

Need Appellate Counsel?

Lotus Appellate Law handles appeals before the Utah Court of Appeals, Utah Supreme Court, California Court of Appeal, and the United States Court of Appeals for the Tenth Circuit.

Related Court Opinions

    • Utah Court of Appeals

    Montes v. National Buick GMC, Inc.

    May 4, 2023

    An integration clause in a purchase agreement precludes enforcement of a separate arbitration agreement signed contemporaneously when the integration clause states the purchase agreement comprises the complete and exclusive statement of contract terms.
    • Contract Interpretation
    • |
    • Evidence and Admissibility
    Read More
    • Utah Court of Appeals

    State v. Soto

    September 1, 2022

    Trial counsel did not render constitutionally ineffective assistance by failing to object to certain testimony where defendant could not establish both deficient performance and prejudice under Strickland v. Washington
    • Evidence and Admissibility
    • |
    • Ineffective Assistance of Counsel
    • |
    • Preservation of Error
    • |
    • Sufficiency of Evidence
    Read More
About these Decision Summaries

Lotus Appellate Law publishes these summaries to keep practitioners informed — not as legal advice. Each case turns on its own facts. If a decision here is relevant to your matter, we’re happy to discuss it.