Utah Court of Appeals · Published Opinion

Can I skip my contract’s dispute process and go to court? Willow Creek Assoc. v. Hy Barr Inc.

2021 UT App 116No. 20200260-CADecided Nov 4, 2021Affirmed

Summary

In Willow Creek Assoc. v. Hy Barr Inc., an apartment owner sued its remodeling contractor and the contractor's president. It brought eleven claims that it had never sent through the dispute process the contract required. The Utah Court of Appeals held that the contract's process covered every claim "arising out of or relating to" the contract, and that phrase is read broadly. The claims should have gone to that process first, so the district court was right to dismiss them. The court also held that it had no power to consider arguments Willow Creek raised only after it filed its appeal.

Key takeaways

The Court of Appeals sided with Hy Barr and its president, Hyrum Barlow, and upheld the dismissal of Willow Creek’s claims.

  • A contract clause covering claims “arising out of or relating to” the contract is read broadly, and here it covered every claim Willow Creek brought.
  • Claims covered by the clause had to go through the contract’s dispute process before they could be brought in court.
  • Arguments first made in a post-judgment motion, after the notice of appeal was filed, could not be considered without a new or amended notice of appeal.

What happened?

Willow Creek Associates owns an apartment complex. In 2017 it hired Hy Barr Incorporated to remodel the apartments. Hyrum Barlow is Hy Barr’s president and was named in the contract as the contractor’s representative.

The contract set out a dispute process. Any claim “arising out of or relating to” the contract went first to an “Initial Decision Maker,” which was an architectural firm on the project. Mediation and then arbitration came next. Arbitration is a private process where someone other than a judge decides the dispute.

In 2019 a subcontractor sued, saying it had not been paid for materials. Willow Creek sent one claim to the Initial Decision Maker, which decided that Hy Barr owed Willow Creek $648,734.78. Willow Creek then filed twelve claims in court against Hy Barr and Barlow. Eleven of them had never gone to the Initial Decision Maker.

What did the district court do?

It entered judgment against Hy Barr on the claim that had gone through the process. It dismissed the other eleven claims because Willow Creek had not taken them to the Initial Decision Maker first.

After Willow Creek appealed, the Initial Decision Maker declined to decide the claims. Willow Creek then asked the district court to undo its dismissal under rule 60, a rule that lets a court relieve a party from an order. Willow Creek argued that the refusal was new evidence and that arbitration agreements cannot be enforced against fraud claims. The district court denied that request.

What did the Court of Appeals decide?

It affirmed. The phrase “arising out of or relating to” is broad and covers any claim with “some logical or causal connection” to the contract. Willow Creek’s claims about unpaid subcontractors and poor workmanship tied directly to promises in the contract. Willow Creek did not dispute that Barlow counted as the “Contractor,” so claims against him were covered too.

Willow Creek also argued that it was unfair to send legal claims to an architect. The court said that argument was not properly raised in the district court. It added that the parties had agreed to that order of steps anyway.

What about the arguments raised after the appeal was filed?

The court could not consider them. Willow Creek raised them only in its rule 60 motion, after it had filed its notice of appeal, which is the paper that starts an appeal. Willow Creek never filed a new or amended notice of appeal after the district court denied that motion, so the Court of Appeals lacked jurisdiction, meaning the legal power, to review those points.

What happens now?

The dismissal stands, along with the judgment against Hy Barr. The case was not sent back.

What should people take from this?

When a contract sends disputes to a set process first, a court may dismiss claims that skip it. A party that wants an appeal to cover a later ruling needs to file a notice of appeal from that ruling too.

Bottom line

Affirmed (Tenney, J., joined by Orme and Harris, JJ.). Willow Creek’s claims “arose out of or related to” the construction contract, so they had to go first to the Initial Decision Maker, and the district court correctly dismissed them (¶¶ 28, 51). The court lacked jurisdiction over arguments first raised in a rule 60 motion decided after the notice of appeal (¶¶ 29, 55).

Issue 1: Scope of the dispute-resolution clause (correctness, ¶ 26): affirmed (no error)

All of the unsubmitted claims fell within the clause, so dismissal for failure to submit them to the Initial Decision Maker was correct. The court asks whether there is an enforceable agreement and which claims the parties intended to arbitrate, with a liberal reading in favor of arbitration (¶¶ 32–36). Willow Creek conceded the agreement existed and that Barlow, the “Contractor’s representative,” was a “Contractor,” so claims against him personally were covered (¶¶ 37–40).

On scope, the court relied on dictionary definitions and held that “relating to” broadens “arising out of”; a claim “need only have some logical or causal connection” to the agreement (¶¶ 44–46, quoting In re Remicade (Direct Purchaser) Antitrust Litig., 938 F.3d 515, 524 (3d Cir. 2019)). It noted that Prima Paint Corp. v. Flood & Conklin Mfg. Co., 388 U.S. 395, 406 (1967), read the same phrase to cover fraudulent-inducement claims (¶ 47). The claims about unpaid subcontractors and workmanlike performance tracked specific contract provisions (¶¶ 48–51).

The argument that the clause is unfair because the Initial Decision Maker lacks legal expertise was unpreserved under Donjuan v. McDermott, 2011 UT 72, ¶ 20, 266 P.3d 839, and no exception was argued (¶ 51 n.10). In any event, the contract let the Initial Decision Maker say it could not resolve a claim, and “a court may not make a better contract for the parties” (¶ 51 n.10, quoting Ted R. Brown & Assocs., Inc. v. Carnes Corp., 753 P.2d 964, 970 (Utah Ct. App. 1988)).

Issue 2: Appellate jurisdiction over the rule 60 arguments (none stated, ¶¶ 52–55): no jurisdiction

The court lacked jurisdiction over arguments first raised in the rule 60 motion. Under Utah R. App. P. 4(b)(2), a notice of appeal filed before a rule 60 motion is decided reaches only the underlying judgment; review of the rule 60 ruling requires a new or amended notice (¶ 54, citing Li-Huang Pon v. Brewer, 2020 UT App 99, ¶ 7, 468 P.3d 581, and Dole v. Dole, 2018 UT App 195, ¶ 40, 437 P.3d 464). Willow Creek filed none (¶ 55).

Not reached

Issue 3: Willow Creek’s arguments that requiring it to use an Initial Decision Maker that declined to act was inconsistent with “substantial justice,” and that arbitration agreements cannot apply to fraud claims, were not reached for lack of jurisdiction (¶¶ 52–55). Plain error was not argued, so it was not before the court (¶ 55 n.12). The court added that any error was not obvious: Energy Claims Ltd. v. Catalyst Inv. Group Ltd., 2014 UT 13, 325 P.3d 70, involved a contract “entered into fraudulently,” and Willow Creek alleged only fraud in later business dealings (¶ 55 n.12).

Takeaways

  • “Arising out of or relating to” reaches claims with any logical or causal connection to the contract, including tort and statutory claims tied to contract duties (¶¶ 46, 51).
  • A clause naming the contractor’s “authorized representative” as the “Contractor” can bind claims against that individual (¶¶ 38–39).
  • After a post-judgment motion is decided, file a new or amended notice of appeal, or the issues it raised are outside appellate jurisdiction (¶¶ 54–55).
  • An unfairness objection to a dispute process needs developed argument and authority below (¶ 51 n.10).

Utah cases relied on

Read the full opinion (PDF)

Case details

Case name
Willow Creek Assoc. v. Hy Barr Inc.
Court
Utah Court of Appeals
Citation
2021 UT App 116
Case no.
20200260-CA
Filed
2020
Decided
November 4, 2021
Opinion type
Authored
Who appealed
Willow Creek Assoc.
Disposition
Affirmed
At stake
Willow Creek's cross-claims against its remodeling contractor Hy Barr and Hy Barr's president, Hyrum Barlow, dismissed for not first going through the contract's dispute-resolution process.

The panel

Ryan D. TenneyAuthor
Ryan M. HarrisConcurred
Gregory K. OrmeConcurred
Trial courtThird District Court, Tooele Department
Trial judgeMatthew D. Bates

Parties

Willow Creek Associates of Grantsville LLCAppellant
Hy Barr Incorporated and Hyrum BarlowAppellee

Holding

A contract clause requiring claims "arising out of or relating to" the contract to go first to an Initial Decision Maker is read broadly and covered all of Willow Creek's claims against the contractor and its representative, so their dismissal was proper; arguments raised first in a rule 60 motion decided after the notice of appeal were outside appellate jurisdiction absent a new or amended notice of appeal.

Practice Tip

If a rule 60 or other post-judgment motion is decided after the notice of appeal is filed, file a new or amended notice of appeal from that ruling; otherwise the court lacks jurisdiction over issues raised only in the motion (¶¶ 54–55).

Need appellate counsel?

Lotus Appellate Law handles appeals before the Utah Court of Appeals, Utah Supreme Court, California Court of Appeal, and the United States Court of Appeals for the Tenth Circuit.

About these Decision Summaries

Lotus Appellate Law publishes these summaries to keep practitioners informed — not as legal advice. Each case turns on its own facts. If a decision here is relevant to your matter, we’re happy to discuss it.