Utah Court of Appeals · Published Opinion

Can a seller back out of a land sale over vague price terms? Regal RealSource v. Enlaw

2024 UT App 95No. 20230368-CADecided Jul 11, 2024Aff’d/Rev’d in part

Summary

In Regal RealSource v. Enlaw, the developer Enlaw agreed to sell Regal 19.46 acres for $4,378,500 and later refused to close. The district court ruled that the contract was too vague to enforce and ordered Regal to remove its notice of the lawsuit from the land records. The Utah Court of Appeals reversed those rulings. It held that the price terms might be enforceable once the facts are developed and that the closing deadline had not started. Some questions about what the parties meant remain for the district court.

Key takeaways

The Court of Appeals mostly sided with Regal, the buyer, by reviving its claim to force the land sale and sending the case back.

  • A contract term that can be read more than one way does not automatically make the contract unenforceable. Courts can look at evidence of what the parties meant.
  • A price set by an agreed process, such as choosing among construction bids, can be definite enough to enforce.
  • Regal’s claim to force the sale, and its notice of the lawsuit on the land, are back in place while the case continues.

What happened?

Enlaw is developing a community called Black Desert. In 2019 it agreed to sell Regal, another developer, about 19.46 acres for $4,378,500 under a real estate purchase contract (the REPC). In an addendum, Regal took on building part of a road. The price would be reduced by “the cost to complete these improvements,” based on bids Regal would gather and the parties would agree on.

In a second addendum, the parties pushed the closing date to 45 days after the City gave “final approval of Buyer’s development project.” In September 2021 the City approved Enlaw’s master development agreement for all of Black Desert. Enlaw said that approval started the 45-day clock, that Regal missed it, and that it would not sell.

Regal sued for specific performance, a court order requiring Enlaw to complete the sale. It also recorded a lis pendens, a notice in the land records that the property is the subject of a lawsuit.

What did the district court do?

Before discovery was finished, it ruled on early motions (summary judgment, meaning a ruling without a trial). It held that the price-reduction terms were too vague to enforce and that Regal had failed to close on time. It ordered the lis pendens removed.

What did the Court of Appeals decide about the price?

It reversed. A term that can be read more than one way does not by itself sink a contract. Courts can look at outside evidence of what the parties meant. Here, the contract set out a process: Regal would gather bids, the parties would pick one, and that bid would set the price reduction. That process could make the price definite enough to enforce, even through specific performance. But Regal did not win this point outright either, because the facts about what the parties intended still have to be developed.

What about the closing deadline?

The court held that “Buyer’s development project” plainly meant Regal’s own project, not Enlaw’s master agreement for the whole community. So the 45-day clock had not started when Enlaw said it did. The court rejected Enlaw’s arguments that the extension lacked consideration (something of value given in exchange) and that it broke the rule against perpetuities, a rule that limits how long property can be tied up.

It did not decide whether Regal’s project has been finally approved yet. The contract is unclear about which City approvals count, so that remains a question of fact.

What happens now?

The lis pendens stays, because Regal’s claim to buy the land is alive again. The case goes back to the district court to sort out what the parties meant. Attorney fees will be decided by the district court when the case ends.

What should people take from this?

When a deal sets a price through a later process, such as choosing a bid, that can be definite enough to enforce. But unclear wording can still lead to a fight over what the parties meant.

Bottom line

Affirmed in part, reversed in part, and remanded (Harris, J., joined by Luthy and Oliver, JJ.), on interlocutory appeal. The court clarified that specific performance “remains potentially available” even when the contract language is not completely free of doubt, vagueness, or ambiguity (¶ 34). It reinstated Regal’s specific performance claim, held as a matter of law that the closing deadline was not triggered by the City’s approval of Enlaw’s MDA, and reversed the lis pendens release (¶¶ 60–62).

Issue 1: Enforceability of the price provisions (correctness, ¶ 18): affirmed in part, reversed in part

The court reversed the summary judgment declaring the REPC unenforceable but affirmed the denial of Regal’s competing motion. Ambiguity usually makes the meaning of a contract a question of fact. It does not make the contract unenforceable unless the essential terms remain indefinite after the court considers parol evidence (¶¶ 21–26). Specific performance requires terms certain enough to frame an order, not absolute certainty (¶¶ 29–31). The “free from doubt, vagueness, and ambiguity” language in Tooele Assocs. Ltd. P’ship v. Tooele City, 2011 UT App 36, ¶ 2, 251 P.3d 835, traces to a case that predates Reed v. Alvey, 610 P.2d 1374 (Utah 1980) (¶¶ 33–34).

Applying those principles, the “other improvements” are fixed by a definite method, the regulating entities’ requirements (¶ 38, following Coulter & Smith, Ltd. v. Russell (Coulter & Smith II), 1999 UT App 55, ¶ 15, 976 P.2d 1218). The bid-selection process is an agreed method for setting the price reduction. That makes this case more like Turley v. Childs, 2022 UT App 85, ¶¶ 38–39, 515 P.3d 942, than Bloom Master Inc. v. Bloom Master LLC, 2019 UT App 63, 442 P.3d 1178 (¶¶ 39–41). Contingencies that have not yet occurred do not defeat enforceability, and the implied covenant of good faith applies (¶ 42). Regal’s reading allowing post-closing true-ups for cost-plus bids or change orders is reasonable (¶¶ 43–45). Because discovery was incomplete, Regal was not entitled to summary judgment (¶ 46). The court did not reach severability (¶ 46 n.3).

Issue 2: The closing deadline (correctness, ¶ 18): affirmed in part, reversed in part

“Entitlements” in Addendum 2 unambiguously means final approval of Regal’s project, not the MDA. The court reversed the timely-closing ruling and directed entry of partial summary judgment for Regal on that point (¶¶ 48–51, 55, 61). The addendum refers to “Buyer’s” project, and the MDA gave no final approval for any specific project on the Property (¶¶ 49–50). The addendum was supported by consideration, including a shorter 45-day closing window (¶ 52). An implied reasonable-time term defeats the rule-against-perpetuities argument under Utah Code § 75-2-1203(1) (¶¶ 53–54 & n.4). Which City approvals trigger the deadline remains ambiguous, so the court affirmed the denial of Regal’s request for a declaration that it has not yet received the Entitlements (¶ 56).

Issue 3: Lis pendens (correctness, ¶ 18): reversed

With the specific performance claim reinstated, there is no current basis to release the lis pendens. The claim affects title under Utah Code § 78B-6-1303(1)(a), so Regal may keep the notice of record while the claim remains alive (¶¶ 58–59).

Issue 4: Regal’s request for attorney fees (none stated, ¶ 59 n.5): remand guidance

Regal’s request for fees under the REPC’s prevailing-party clause is premature. The district court will decide entitlement when the litigation concludes, citing Crank v. Utah Jud. Council, 2001 UT 8, ¶ 44 n.18, 20 P.3d 307 (¶ 59 n.5).

Takeaways

  • Ambiguity in an essential term calls for parol evidence, not a ruling of unenforceability on summary judgment (¶¶ 21–22, 46).
  • A price fixed by an agreed process, such as selecting a bid, is not an unenforceable agreement to agree (¶¶ 40–41).
  • Defined party labels such as “Buyer” can resolve which approval triggers a deadline as a matter of law (¶¶ 48–49).
  • A lis pendens survives as long as a specific performance claim affecting title remains alive (¶ 59).

Utah cases relied on

Read the full opinion (PDF)

Case details

Case name
Regal RealSource v. Enlaw
Court
Utah Court of Appeals
Citation
2024 UT App 95
Case no.
20230368-CA
Filed
2023
Decided
July 11, 2024
Opinion type
Authored
Heard
Argued May 28, 2024
Time to decision
44 days after argument
Who appealed
Regal RealSource
Disposition
Affirmed in Part, Reversed in Part
At stake
Regal's claim for specific performance of a $4,378,500 contract to buy about 19.46 acres of undeveloped land from Enlaw, and its lis pendens on the land.

The panel

Ryan M. HarrisAuthor
John D. LuthyConcurred
Amy J. OliverConcurred
Trial courtFifth District Court, St. George Department
Trial judgeEric A. Ludlow

Parties

Regal RealSource LLCAppellant
Enlaw LLCAppellee

Holding

A real estate purchase contract whose price reduction is set by an agreed bid-selection process is not unenforceable as a matter of law, specific performance remains potentially available despite facial ambiguity, and a closing deadline tied to approval of "Buyer's development project" was not triggered by approval of the seller's master development agreement.

Practice Tip

When opposing early summary judgment on indefiniteness, show the agreed method for fixing the open term and point to the need for extrinsic evidence of intent; specific performance does not require language free of all ambiguity (¶¶ 34, 41, 46).

Need appellate counsel?

Lotus Appellate Law handles appeals before the Utah Court of Appeals, Utah Supreme Court, California Court of Appeal, and the United States Court of Appeals for the Tenth Circuit.

About these Decision Summaries

Lotus Appellate Law publishes these summaries to keep practitioners informed — not as legal advice. Each case turns on its own facts. If a decision here is relevant to your matter, we’re happy to discuss it.